IH 35 SB (Wednesday Night – November 28th)
• Place Full Main lane closure on IH 35
• Exit traffic SB ML traffic to frontage road at FM 1103.
• Traffic to enter IH 35 SB at entrance ramp past FM 1103 intersection.
• Stage law enforcement
o at the intersection of the NB & SB frontage road and FM 1103
• Once beams are hung and cross bracing is placed and beams are secured, place interstate traffic in original configuration prior to ML closure.
Beams will be staged on the outside lane of the SB frontage road before the entrance ramp at IH 35 Southbound Exit 182, just past Marigold Way the morning of the closure.
IH 35 NB (Thursday Night – November 29th)
• Full Main lane closure on IH 35
• Exit IH 35 NB ML traffic to frontage road at FM 1103.
• Traffic to remain on frontage road thru the FM 1103 intersection where they can enter the Interstate past this intersection.
• Stage law enforcement
o at the intersection of the NB & SB frontage road and FM 1103
• Once beams are hung and cross bracing is placed, and beams are secured, place interstate traffic in original configuration prior to ML closure.
Beams will be staged on the outside lane of the NB frontage road before the entrance ramp to IH 35 NB at FM 2252 the morning of the closure.