Building Permit Requirements
- Three (3) complete sets of Engineer / Architect stamped plans.
- Commercial Energy Compliance Checklist (CommCheck)
- TDLR Architectural Barriers (A/B) Project Registration Number
- Reed Fire Protection Review
- Digital As Built Plans (once project is completed)
Plan Review
- Building Codes / Amendments
- Building Review (City Staff) - Minimum forty-five (45) business days
- Fire Protection Reviews - Please contact City staff for information
Includes, but not limited to:
Fire Protection
Fire Alarm
Fire Sprinkler
Fire-line
Building Permit Fees
- Fees - See Schedule A (Building Permit Fee Schedule)
Impact Fees at Building Permit - Ord. #1067 (Please contact City staff for calculations)
- Drainage - Section 3.3.3 Drainage
- Transportation - Section 3.3.4 Transportation
- Wastewater - Section 3.3.2 Wastewater
- Water - Section 3.3.1 Water
Cibolo Creek Municipal Authority Fee (CCMA)
- CCMA provides to City plus $15.00 Administrative Fee
City Water Fees - See Ordinance #1114
- Water Meter - based on number and size of meter(s)
- Water Deposit - based on number and size of meter(s)
- Water Meter Install Fee - based on number and size of meter(s)
Other Possible Fees - See Schedule A
- Fire Alarm Permit Application
- You may apply for the Fire Alarm Permit once RFP has completed the review. Please provide one (1) stamped set of reviewed plans along with a copy of the Review Letter.
- Fire Line Permit Application
- You may apply for the Fire Line Permit once RFP has completed the review. Please provide four (4) stamped sets of reviewed plans along with a copy of the Review Letter.
- Fire Sprinkler / Suppression Permit Application
- You may apply for the Fire Sprinkler Permit once RFP has completed the review. Please provide one (1) stamped set of reviewed plans along with a copy of the Review Letter.